Nº309
A 1.29 MWh hybrid system at the Rivelli farm
Powersafe and Zipp Energia have commissioned a hybrid system at Rivelli Alimentos' breeder farm in Carmo do Cajuru (MG): six Huawei cabinets with 1.29 MWh, a 378 kWp plant, the Cemig D grid and a diesel generator. According to Canal Solar, it is the first private-customer BESS in the state with full approval from the distribution utility.
The estimated saving, around 50% of the bill, comes from capping demand at 360 kW, shifting consumption out of the peak and correcting the power factor. None of this has a contracted term. The value follows the tariff, reviewed every year by ANEEL: in the Cemig D adjustment approved on 26 May 2026, the average effect was 6.50%, and 9.43% at high voltage.
For those assessing behind-the-meter batteries, the calculation rests on an assumption that changes with each tariff cycle. The other part of the value is independent of adjustments: around 10 hours of autonomy for critical loads and up to 27 hours with non-essential loads shed.
Full approval opens the way for other consumers in Minas Gerais. The saving is an estimate. Production continuity is already installed.
Translated from the Portuguese original published by Linus Green Energy.
SourcesCenário Energia, ANEEL aprova reajuste tarifário da Cemig com efeito médio de 6,50%, 27/05/2026, https://lnkd.in/dxe3pvPt; Atlas Público, Resolução Homologatória nº 3.589, 26/05/2026, https://lnkd.in/d5kdwuyq