StorageEN · PT

Nº194

The 15-minute load curve and the commercial BESS business case

Post commented onPost by Marcio Takata: “35.040 pontos podem dizer mais sobre um projeto de BESS do que 12 contas de…” See the full post in the Linus publication ↗

The assessment of a commercial BESS usually begins with the electricity bill and ends with the IRR. Marcio Takata, CEO of Greener, argues that the load curve in short intervals says more than twelve bills: a 500 kW peak for fifteen minutes and the same peak for three hours call for the same power and different energy.

The regulatory yardstick confirms the starting point. ANEEL Normative Resolution 1,000, of 7 December 2021, defines measured demand as the highest active power integrated over fifteen-minute intervals in the billing period. One year at that interval gives the 35,040 points cited in the post.

The effect does not stop there. Dispatch and depth of cycle determine degradation, which defines how much replacement and maintenance the project carries until the end of the contract. A system sized by monthly bill delivers the promised savings in the first year and loses margin when usable capacity falls.

The assumption that pays the return lies in measurement before it lies in the spreadsheet. Before contracting, it is worth requiring the fifteen-minute load curve and the degradation curve for the expected cycling profile.

Translated from the Portuguese original published by Linus Green Energy.

SourcesANEEL, Resolução Normativa nº 1.000/2021, art. 2º, inciso XIII, 07/12/2021, https://lnkd.in/dZ2h-PCS

Original post. This analysis was published on the Linus Green Energy page on LinkedIn. Open on LinkedIn ↗